Bluefield Sewer Improvements

Bluefield Sewer Improvements

Project Description

Construction of a new 1,600 GPM sewer lift station, 11,000 LF of 16" Force Main and 4,600 LF of 12" Force Main. This will divert flows from the Pelion/SC 6 Corridor and the Bluefield Pump Station to the proposed 24" Gravity Sewer along Old Orangeburg Road.

Project Engineer

Hazen and Sawyer

Project Contractor

  • McMahan Bros Construction
  • Shady Grove Construction